The freeway ramp closures will begin Friday and Saturday nights at 7 p.m. as crews rebuild the Mullholand bridge.

More overnight closures are planned beginning Friday night on the San Diego (405) Freeway through the Sepulveda Pass as work continues on a $1.2 billion improvement project.

The southbound freeway will be closed from the Ventura (101) Freeway to Getty Center Drive Friday and Saturday nights as crews continue to work on rebuilding the Mulholland bridge across the 405.

Some freeway ramps in the area could begin closing as early as 7 p.m. Friday and Saturday, and some lanes could be blocked beginning at 10 p.m. All southbound lanes will be closed at midnight, but the closures should be lifted by 5 a.m.

Find out what's happening in Venice-Mar Vistawith free, real-time updates from Patch.

The closures will impact the northbound lanes between Getty Center Drive and Ventura Boulevard on Monday and Tuesday nights. More southbound closures are planned on the nights of March 12 and 13.

According to Metro, which is overseeing the project, Sepulveda Boulevard will remain open during the freeway closures and will be available as an alternate route.

Find out what's happening in Venice-Mar Vistawith free, real-time updates from Patch.

The project will add carpool lanes to the freeway and make other improvements, including the reconstruction of major bridges over the 405 in the Sepulveda Pass. The overall project is scheduled to be completed next year.